2002 ARC Merit Award
Woodlawn Chilled Water Plant
Woodlawn, Maryland

Presented to the H.F. Lenz Company for the innovative use of 3D modeling in developing the mechanical systems for a retrofit of the U.S. Social Security Administration's chiller plant.

The project objectives and requirements included:  improving the reliability and redundancy of the plant; providing for the maintainability of the facility; improving the operating efficiency and controllability of the plant; and minimizing the impact of the modernization process on the daily operation of the facility.

To provide the best solution for addressing the existing chiller plant deficiencies and meet GSA's project objectives, the H.F. Lenz Company thoroughly evaluated four options.  The newly renovated chilled water plant accomplished all of the following:
 
bullet

Supplied sufficient capacity to address projected future loads

bullet

Utilized a simplistic piping and equipment arrangement

bullet

Provided redundancy during a majority of the cooling season

bullet

Required the least amount of maintenance

bullet

Simplified the control system

The plant was contained in a fixed-space area, which was already tightly packed with equipment.  Highly detailed 3D models were developed of the existing equipment layout including piping, equipment, conduit, structural members, etc.  This allowed H.F> Lenz Company to work through the space constraints while precisely placing equipment, verifying pipe routing; maintaining clearances required for future equipment installation; and identifying phasing schemes to allow the plant to remain in service during construction.  The drawings provided the General Services Administration and the Social Security Administration with a detailed visualization of the project during design. This resulted in less confusion during the bidding process, and ultimately, more accurate and competitive bids.  Through team work and coordination, the chilled water plant renovation was completed on time and within budget.

 

Consulting-Specifying Engineer Article
Read the article!


3D CADD modeling was utilized to develop the dimensional requirements of the secondary pumping system


An extensive three dimensional survey was conducted to create a working model of the chilled water plant


 

 

 